FIDIC合同 | 通用条件雇主的接收篇中“Interference with Tests on Completion(对竣工试验的干扰)”的释义(3)

 

If the Contractor suffers delay and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20. 1 [Contractor's Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

如果由于进行竣工试验的此项延误,使承包商遭受延误和(或)招致增加费用,承包商应向工程师发出通知,并应有权根据第20.1款[承包商的索赔]的规定要求:

(a)根据第8.4款[竣工时间的延长]的规定,如竣工已或将受到延误,对任何此类延误给予延长期;以及

(b)任何此类费用加合理利润,应计入合同价格,给予支付。


(参考资料来源:《施工合同条件1999年第1版》,机械工业出版社出版,国际咨询工程师联合会、中国工程咨询协会编译。)